Hello All,
I have a requirement to transfer the PR from ECC to SRM , I would like to know the method for the same and the configuration steps
I have Tried it with program BBP_EXTREQ_TRANSFER and has done the required Configuration steps as below as given in the note 1646982
You need to create necessary customising on ECC MM side at following path of table SPRO:
Integration with Other SAP Components -> Supplier Relationship Management -> Plan-Driven Procurement
- Maintain Profiles for External Procurement (table T160PR)here You need to set the external logical (SRM) system to the profile (EPROFILE)
- Control External Procurement (table T160EX)
I have configured the NDI, as given in the note 656597
In the EBAN Table The E profile Field is blank and could any one guide me how to go further in this regard
we donot have the PI system
Thanks in Advance