Hi,
We are planning to use SRM 7 EHP 1 with backend ECC 6 EHP 4. We are leaning toward the extended classic scenario. However we are a bit confused reading some documentation that saying Service Procurement classic can only be used in classic scenario.
What does this mean? To put this in more simple, can we have this scenario in extended classic deployment:
PDP:
1. We create PR with 2 items, each item have 3 sub-line services,
2. We push this PR to SRM
3. We create PO in SRM and it is copied to ECC.
4. PO will have 2 items, with each item have 3 sub-line services.
Self Service Procurement:
1. We create SC with 2 items, each items have 3 sub-line services,
2. We create PO in SRM and it is copied to ECC
3. PO will have 2 items, with each item have 3 sub-line services.
Really appreciate if someone can clarify this point.
Best regards,
Josh