Hi Friends,
Please help me out for one of the query I am facing:
1) SC created with one product category by the requester.
2) As per the request, requester making changes in the prod.category at that time vendor is missing, Requester getting error vendor missing , requester filling the field and user able to order the SC.
3) After that SC goes to SC completion approval level and all the other approval levels and the SC gets approved.
4) But SC will goes into item in process.
When that SC comes to our end to check why the SC is in "Item in process" we able to recognize this is due to vendor missing.
"To understand this thing we had a screen sharing with the requester, To check whether user is directly ordering without checking the "CHECK " button and check is missing, when the requester change the prod.cat and try to order it then we are getting error , we are not knowing where exactly the vendor is missing."
As workaround we are SC completion team to add the vendor but we are looking a permanent solution.So some one help me out.
Thanks in advance.
Thanks & Regards,
Pramod.