Quantcast
Viewing all articles
Browse latest Browse all 3184

SRM MRP for contracted material

hi,

 

we are using SRM 5.0 extended classic and ECC6.0 as backend. we are currently implementing MRP function in ECC6.0 were PR converted to shopping cart in SRM. our problem is for the contracted material. since contract is in SRM side, PRs created in ECC will in no way to can refer to a contract and automatically create a PO. what we wanted is if a material have a contract in SRM, when the PR is transferred to SRM SC it will automatically call-off a contract and create a PO. is this possible? if so, can anyone share how to do it? thanks in advance.

 

vincent


Viewing all articles
Browse latest Browse all 3184

Trending Articles