Hello All,
Is there a way to put a Hard Stop during Process all/ selected draft during Sourcing 3 rd stage.
We have made some validations on the PO based on price in the BBP_DOC_CHECK_BADI. The PO should not be created if the criteria is not met.
This is working when the user selects - Edit Selected Draft.
However when the user selects Process All Draft/ Process Selected Draft, the error is coming up, however the PO still gets created. There is no hard stop for the PO creation, when the user selects Process All Draft/ Process Selected Draft. Has anyone worked on such a requirement before? Please let us know.
Thanks, M