Dear SAP SRM Guru's,
I want to ask about cfolder in two envelope process, i configured cfolder base on sap help, and what i read in SCN
The process that i understand are:
1. Purchaser with role SAP_CFX_USER and SAP_CFX_COMP_CREATOR, create RFX, automatically a in cfolder system will create a folder called a technical details in collaborative scenario,
- My question are : can we automatically change the name of the folder? or we have to change it manually?
2. after the rfx publish, the bidder with role SAP_CFX_USER will create the technical rfx response, the cfolder system will automaticallly create a folder in the technical detail folder created by the purchaser, the folder will be name based on username bidder, maybe the structure will be like below
-Technical Details
-- Technical_bid
--- Supplier2
---- Tech_bid
My problem for this process are :
- when i log on using the bidder user, i cannot see the technical details folder, so after that i log on using adminstrator, and gave authorization to the bidder user in Technical Details, after that i can see the technical detail folder, is it the correct way to use the cfolder? so i have to gave authorization manually to the bidder?
- may next problem is when i have two bidder, the bidder can see other bidder folder, is it the behaviour or there something i miss?
can someone help me?